-
An
Adjudication under the Housing Grants Construction and Regeneration Act
1996 and the Scheme for Construction Contracts. The contract was a JCT
IN/SC First Edition 1985 standard form of contract. Represented the
Referring Party in the recovery of £26,000 in which a settlement was
achieved recovering 75% of the amount claimed. Issues addressed in this
adjudication included Variations and Measured Works. The primary issues
was lack of notice of deduction by the Other Party.
-
An
Adjudication under the Housing Grants Construction and Regeneration Act
1996 and the Scheme for Construction Contracts. The contract was a DOM/1
standard form of contract. Represented the Responding Party in the
recovery of a sum of £630,000 in which a decision was given by the
Adjudicator ordering immediate payment of 100% of the amount claimed.
Issues addressed in this adjudication included Variations and Measured
Works. The primary issues was lack of notice of deduction by the Other
Party.
-
An
Adjudication under the Housing Grants Construction and Regeneration Act
1996 and the Scheme for Construction Contracts. The Contract was a JCT
IN/SC First Edition 1985 standard form of contract. Represented the
Other Party in which £35,000 was claimed by the Referring Party. The
matter was settled prior to the Adjudicator’s decision with no payment
to be made by either party. Issues addressed in this adjudication
included Loss and Expense, Extension of Time Variations and Measured
Works. The primary issue was interpretation of the Contract.
-
An
Adjudication under the Housing Grants Construction and Regeneration Act
1996 and the Scheme for Construction Contracts. The Contract was a DOM/1
standard form of contract. Represented the Referring Party in the
recovery of a sum of £56,000 in which a settlement was achieved prior
to the Adjudicator decision recovering payment of 70% of the amount
claimed. Issues addressed in this adjudication included Variations and
Measured Works. The primary issue was lack of notice of deduction by the
Other Party.
-
An
Adjudication under the Housing Grants Construction and Regeneration Act
1996 and the Scheme for Construction Contracts. The Contract was a JCT
1980 standard form of contract. Represented the Referring Party in
recovery of a sum of £292,000 in which a settlement was achieved
recovering 100% of the amount claimed. Issues addressed in this
adjudication included Loss and Expense, Extension of Time, Variations
and Measured Works. The primary issue was lack of notice of deduction by
the Other Party.
-
An
Adjudication under the Housing Grants Construction and Regeneration Act
1996 and the Scheme for Construction Contract. The Contract was for a
sum of £139,000 in which a settlement was achieved recovering payment
of 100% of the amount claimed. Issues addressed in this adjudication
included Variations and Measured Works. The primary issue was lack of
notice of deduction by the Other Party.
-
An
Adjudication under the Housing Grants Construction and Regeneration Act
1996 and the Scheme for Construction Contacts. The Contract was the
Other party’s own standard terms and conditions. Represented the
Referring Party in the recovery of a sum of £159,000 in which a
decision was given by the Adjudicator ordering immediate payment of £50,000.00
the other sums claimed did not form part of the Adjudicator’s decision
and are being readjudicated. Issues addressed in this adjudication
included Variations and Measured Works. The primary issue was lack of
notice of deduction by the Other Party.
-
An
Adjudication under the Housing Grants Construction and Regeneration Act
1996 and the Scheme for Construction Contracts. The Contract was the
standard terms and conditions of the Other Party. Represented the
Responding Party in the defence of a claim for £260,000. The
Adjudicator awarded £100,000 to the Referring Party. Issues addressed
in this adjudication included Loss and Expense, Extension of Time,
Variations and Measured Works. The primary issue was interpretation of
the Contract.
-
An
Adjudication under the Housing Grants Construction and Regeneration Act
1996 in accordance with a JCT 1981 standard form of contract with
amendment 12, therefore the Scheme did not apply. Represented the
Referring Party in the recovery of a sum of £1,037,000.00 which is on
going. Issues addressed in this adjudication include Loss and Expense,
Disruption Extension of Time Variations and Measured Works. The primary
issues is lack of notice of deduction by the Other Party.
-
An
Adjudication under the Housing Grants Construction and Regeneration Act
1996 in accordance with a JCT IFC 1984 standard form of contract with
amendment 12, therefore the Scheme did not apply. Represented the
Responding Party in the recovery of a sum of £39,000.00. The
Adjudicator awarded £36,500.00 to the Referring Party. Issues addressed
in this adjudication included Variations and Measured Works. The primary
issue was interpretation of the Contract.
-
An
Adjudication under the Housing Grants Construction and Regeneration Act
1996 and the Scheme for Construction Contracts. The Contract was a RIBA
Blue Book standard form of contract and an oral contract for additional
work recorded in writing. Represented the Referring Party in the
recovery of a sum of £25,500.00. The Adjudicator awarded £16,300.00 to
the Referring Party. Issues addressed in this adjudication included
professional services provided. The primary issue was interpretation of
the Contract.
-
An
Adjudication under the Housing Grants Construction and Regeneration Act
1996 and the Scheme for Construction Contracts. The Contract was given
orally and later recorded in writing. Represented the Referring Party in
the recovery of a sum of £206,500.00 in which a settlement was achieved
prior to the Adjudicator decision recovering payment of £195,000.00.
Issues addressed in this adjudication included Variations and Measured
Works. The primary issue was lack of notice of deduction bu the Other
Party.
-
An
Adjudication conducted by agreement between the parties The Contract was
based on IChemE Red Book.. Executive Director acted as the
Adjudicator in determining a dispute as to contractual interpretation.
Issues addressed in this adjudication included Variations and Measured
Works. The primary issue was contractual interpretation.