Daniel Atkinson Limited 

Main Menu Page
P.O. Box LB 1466     London W1A 9LB    England

Tel: +44 (0) 1689 819 381    Fax: +44 (0) 1689 811 583  Email:daniel@atkinson-law.com

 

Defects    © Daniel Atkinson 1999

 

Definition

Liability Periods

Abatement of Price

Limitation of Liability

Employer's Remedies for Defects

Legal Cases

Limitation of Right of Abatement

Consequential Loss - Limitation of Liability

Definition

Defective work can be described as work which fails to comply with the express descriptions or requirements of the contract, including very importantly any drawings or specifications, together with any implied terms as to its quality, workmanship, performance or design. By definition, therefore, defects are breaches of contract by the contractor.

The general principle is that a defect in construction work amounts to a breach of contract which entitles the Employer to claim damages. The Employer is entitled to recover the financial cost of remedial works for defects carried out either by himself or another contractor. The Contractor’s liability in damages is not limited except by clear words in the Contract.

Employer's Remedies for Defects

The problem of defects can be dealt with in a number of ways. The defective work can be remedied by the Contractor or by the Employer. The Employer may agree a deduction for the Contract price instead of remedying the defect. Even if the defect is to be remedied, the Employer may wish to deduct the cost of remedial works from the contract price until the remedial works are carried out. The contract may make provision for the Employer to withhold retention monies during the construction period, and for this to be released in parts - one part on issue of the Certificate of Completion and the remainder on expiry of the Defects Liability Period. The Employer may also wish to claim for consequential losses arising from the defects either during the defects liability period or in the post-correction period.

Liability Periods

In most standard forms, the liability for defects is dealt with differently for three distinct periods. These three periods are:

(i) the construction period;

(ii) the maintenance or defects correction or defects liability period;

(iii) the post-correction period.

During the construction period the Contractor will have a contractual licence to possession of the site. During this period the contractor will be required to carry out remedial works. The A/E in many standard forms has extensive powers to have defects remedied including removal and substitution of defective materials and removal and re-execution of defective work.

During the defects liability period, which starts on completion of the works, standard forms generally give the Contractor a licence to return to the site for the purpose of remedying defects.

The post correction period starts at the end of the defects liability period. The contractor will no longer have a right of entry nor a right to remedy his own defects, although many standard forms provide a short transition period for the contractor to enter and remedy defects notified up to the end of the defects liability period.

Standard forms therefore give the Contractor the right to remedy his own defects both during the construction period and the defects liability period. This confers substantial benefits on both parties and gives the contractor the right as well as the obligation to correct defects, which in many cases will be less expensive than to have others carry out the remedial work.

Legal Cases

The issues which arise are whether defects which arise during the construction period constitute a breach of contract by the contractor, and whether a failure to give the contractor the opportunity to remedy defects during either the construction period or the defects liability period affects the Employer’s rights to damages. These issues have been addressed in two cases both on the JCT Minor Works form. Clause 2.5 of the form requires the contractor at his own cost to make good defects due to materials and workmanship not in accordance with the contract, which appear within the defects liability period.

In William Tonkinson & Sons Limited -v- the Porochial Church Council of St. Michael and Others (1990), Construction Law Journal Volume 6 No 4 the defects arose in the construction period and the contractor was given notice of them before Practical Completion. The Architect did not however serve on the contractor any notice under Clause 3.5 requiring the contractor to remedy the defects prior to practical completion, but instead the Employer gave instructions to other contractors to remedy the defects, which were completed before Practical Completion.

It was held that the Employer was entitled to recover damages for the defective work as it was still a breach of contract, despite occurring during the construction period. It was considered that if the defects are remedied by the contractor prior to practical completion the contract may be construed impliedly excluding any right to nominal damages in respect of them. Clause 2.5 provides an additional remedy for the Employer ie the right to require the contractor to make good the defects, and not releasing the contractor from his ordinary liability to pay damages for defective work. It was held that workmanship which falls short of the standard required by the Contract and which the Employer remedies prior to practical completion still constitutes a breach of contract. The Employer is entitled to recover damages from the Contractor subject to proof that they were attributable to workmanship or materials which fall below the contractual standard. The amount of damages which the Employer would be entitled to recover however, is not his outlay in remedying the damage, but the cost which the Contractors would have incurred in remedying it if they had been required to do so; the sum is anticipated to be much less than the actual remedial costs.

In Pearce & High Limited v Baxter (1999) Court of Appeal defects had become apparent before the end of the defects liability period, but these were not notified to the contractor. It was accepted that the contractor’s obligation under Clause 2.5 to remedy defects cannot be enforced unless a contractor has notice of the defects. It was held at such notice was a condition precedent to Employer’s right to require compliance with Clause 2.5, but that different considerations might arise if the contractor became aware of the defects from another source. The obligation could not be enforced against the contractor unless he has notice of the defects.

It was held that the absence of notice prevents the Employer enforcing the right to require the contractor to rectify the defect, but subject to the contract terms the defect is still a breach contract with a right to recover damages. Such a right cannot be excluded except by clear, express words or by a clear and strong implication from the express words used.

It was held that the Employer’s failure to comply with Clause 2.5, whether by refusing to allow the contractor to carry out the repairs or by failing to give notice of the defects, limits the amount of damages which he is entitled to recover. As a matter of legal analysis this is either

by permitting the contractor to set-off against the Employer’s damages claim the amount by which he, the contractor, has been disadvantaged by not being able or permitted to carry out the repairs himself; or

by reference to the requirement for the Employer to mitigate the loss for which is entitled to recover damages.

The measure of damages was therefore the cost of repairs by the contractor if he remedied the defects himself on the assumption that this is lower than the cost of repair by a third party.

The absence of notice of the defect does raise the possibility that the measure of damages in some circumstances may only be the diminution of the value of the property by reason of the defect, on normal principles. The decision was not concerned with this aspect however and left the question open.

Common Law Right of Abatement of Price

The Employer will not wish to pay the full contract price first and then counterclaim for damages by way of set-off. Apart from the inconvenience of doing so, the legal fees as well as the cost of the remedial works themselves will create a significant adverse cashflow for the Employer. He will also increase his exposure to the consequences of the Contractor’s possible insolvency, always a serious consideration in the present economic climate. Instead the Employer will wish to deduct the cost of remedial works from the amount due to the Contractor. He has this right at common law to raise a defence of abatement against any action for payment in full by the contractor Slater -v- CA Dumequin Ltd (1992) 29 CON LR 24. This right of abatement only applies to defects which are patent at the time payment is due.

It is suggested that on the basis of Tonkinson above the amount by which the Employer might rightfully reduce the amount due to the Contractor is limited to the cost which the Contractor would have incurred in remedying any defect.

Where the defects are the responsibility of the Contractor and he does not carry out the remedial work within a reasonable time then the Employer is entitled to abate the amount otherwise due to the Contractor, by the amount it would cost the Employer to remedy the defect. This additional liability arises from the Contractor’s further breach of contract in not remedying the defect.

The question as to what is the reasonable cost of remedying a defect received the attention of the Court of Appeal in the case of Ruxley Electonics and Construction Limited -v- Forsyth (1993). It was held that it would be unreasonable to award as damages the reinstatement cost since it would be out of all proportion to any benefit the client would enjoy if the defective work was rebuilt. It was held that to do otherwise the injured party would have recovered not compensation for loss but a very substantial gratuitous benefit. An undertaking by the injured party to spend any damages on remedial works made no difference since one could not create a loss, which does not exist, in order to punish the defendants for their breach of contract. The basic rule of damages, to which exemplary damages are the only exception, is that they are compensatory not punitive.

Limitation of Right of Abatement

During the defects liability period, defects may be discovered. Once the Contractor has remedied those defects which have appeared during the defects liability period, the A/E under standard forms is required to issue a Final Certificate. Some standard forms provide that such a certificate is conclusive of certain matters and particularly that there are no other patent defects and therefore prevents operation of the right abatement of price Westminster City Council -v- Jarvis & Sons Ltd (1970) 1 ALL ER 943.

Limitation of Liability

It is possible to prevent the purchaser from withholding payment of any amount due by reason of set-off due to defects, by incorporating in the contract a suitable exclusion clause. Such a clause must satisfy the test of reasonableness; if it is too wide it will not be effective Stewart Gill Ltd -v- Horatio Myer & Co Ltd (1992) 2 All ER 257 (CA). It is also possible to incorporate a clause to limit liability to the cost of repair and to exclude recovery of damages for consequential loss, but this also is subject to the test of reasonableness Oddment Murray Limited -v- BSP International Foundations Ltd (1992). It will be very difficult in the construction industry to limit the contractor's responsibility to remedy defects in his work on site by say limiting the purchaser's remedy to a six month warranty on goods supplied Charlotte Thirty Ltd -v- Crocker Ltd (1990).

Consequential Loss - Limitation of Liability

Two questions arise in relation to the Final Certificate. The first is whether the Final Certificate prevents the Employer from recovering for the consequential effect of defects which have been remedied either by the Employer or the Contractor before the Final Certificate. The second is whether the Employer is prevented from recovering damages for any defects which become patent after the issue of the Final Certificate - in the post-correction period.

It appears following H W Nevill (Sunblest) Ltd -v- William Press and Son Ltd (1981) 20 BLR 78, that the satisfactory making good of defects does not amount to an exclusion of claims in respect of their consequences. The measure of damages will therefore not only be the cost of repair of the defect, but also such compensation as the loss of the use of the Plant during repairs in accordance with the ordinary rules governing remoteness of damage.

Services

Contacts
Client Recommendations Daniel Atkinson
Disclaimer & Conditions of Use