|
|
Training Programme
Contract Administration
- Morning
- 1.1 THE LEGAL RELATIONSHIP
- Creating the Contract
- - Construction Practice
- - Formailty
- - Contract Formation
- - Best Practice
- Incorporation of Terms
- - Published Contract Forms
- - Subcontract Conditions
- - Main Contract and Subcontract Terms
- - Implied Terms
- Incomplete Express Agreement
- - Essential Terms
- - Contractual Machinery
- - Identification of Terms
- Interpretation of Contract Terms
- - Legal Principles
- - Pre-Contract Discussions
- - Post Contract Conduct
- - Entire Agreement Clauses
- - Exhaustive Remedy Clauses
- 1.2 PAYMENT RIGHTS and OBLIGATIONSM
- Price & Payment
- - Payment under Contract
- - No Express Price
- - Contractual Quantum Meruit
- - Measurement of Price
- Restitution
- - Letters of Intent
- - Work Outside Letter of Intent/Contract
- - Measure
- Afternoon
- 2.3 COMPLETION OF THE WORKS
- Time at Large
- Completion
- 2.4 ACCELERATION & MITIGATION
- When to Accelerate
- Failure to Grant EOT
- Mitigation
2.5 EXTENSION OF TIME
- Standard Forms
- Concurrent Events
- Events After Completion
- Float
- Notice
- Timing of EOT
2.6 FINANCIAL COMPENSATION
- Prolongation Costs
- Head Office Overheads
- Disruption Costs
- Global Method
- Comparison of Norms
- Assessment
- Liquidated Damages
- Types of LDs
- Penalty Rules
- Loss of Right to LDs
- Notices and LDs
- Morning
- 2.1 OBLIGATIONS AS TO TIME
- Employers Obligations
- Express
- Implied Obligation not to Hinder
- Implied Obligation to Cooperate
- Contractors Obligations
- General
- To Complete the Works
- To Progress the Works
- Programme Obligations
- General
- Programme a Contract Document
- Subcontractors and Main Contract programme
- 2.2 CAUSATION
- Causation in Law
- Logical Analysis
- Common Sense
- Dominant Cause
- But-For Test
- Intervening Event
- The Principled Approach
- Concurrency
- Global Claims
- Programme Analysis
- Potential Inaccuracies
- Impacted as-Planned Method
- Time Slice/Windows Method
- As-Built Method
- Afternoon
- 2.3 COMPLETION OF THE WORKS
- Time at Large
- Completion
- 2.4 ACCELERATION & MITIGATION
- When to Accelerate
- Failure to Grant EOT
- Mitigation
2.5 EXTENSION OF TIME
- Standard Forms
- Concurrent Events
- Events After Completion
- Float
- Notice
- Timing of EOT
2.6 FINANCIAL COMPENSATION
- Prolongation Costs
- Head Office Overheads
- Disruption Costs
- Global Method
- Comparison of Norms
- Assessment
- Liquidated Damages
- Types of LDs
- Penalty Rules
- Loss of Right to LDs
- Notices and LDs
- Morning
- 3.1 The Right to Payment
- What are the Purchaser's Obligations as to Payment?
- Can a Letter of Intent or a Bare Agreement with No Agreed Price Create a Contract?
- If No Price is Stated in the Contract What Payment is Due?
- Will a Claim for Quantum Meruit Succeed if a Contract Deals with the Situation?
- What is the Measure of Payment for Work Under Contract Where No Price is Stated?
- If the Contract Does Not mention VAT, Does the Price Include VAT?
- Is Payment Required to be Made if Work is Not Completed?
- How is the Price Valued?
- Is there an Entitlement to Payment for Work Carried Out Beyond the Financial Limit of the Letter of Intent?
- Is There an Entitlement to Payment for Work ""Outside the Contract""?
- When Will the Law Imply an Entitlement to Payment for Requested Work Carried Out Without a Contract?
- Are There Any Situations Where Speculative Work Can Be Reimbursed?
- What is the Measure of Payment When the Work is Not Part of a Contract?
- If Work is not Part of a Contract Can Delays and Defects be taken into Account in the Measure of Any Payment?
- What is the Measure of Reduction in Any Payment for Defects if There Is No Contract?
- 3.2 Administration of Payment
- Is There a Right to Interim Payment?
- If a Section 110 Notice is Not Given in Accordance with the Contract, is Payment Required to be Made in Full on Application?
- Can a Pay When Paid Clause Prevent Payment?
- Can the Failure of A/E to Issue a Payment Certificate Prevent Payment?
- Must the Employer Pay the Amount Stated in an Interim Certificate?
- What is the Effect of a Final Certificate on the Right to Payment?
- When is a Final Certificate Not Valid?
- If a Final Certificate is Issued Late, Is it Still Valid?
- What is the Effect of the Final Certificate of an Adjudicator’s Decision on an Interim Certificate?
- Has the Contractor a Right to Payment for Material on Site but not Fixed?
- If the Employer Becomes Insolvent Must the Contractor Still Pay the Sub-Contractor?
- When is Payment Made?
- Afternoon
- 3.3 The Right to Withhold Payment
- Can an Amount Paid in a Past Certificate, be Deducted from a Later Certificate?
- Is the Employer Required to Place Retention in a Separate Bank Account?
- Can Payment be Reduced Due to Defective Performance?
- What is the Measure of Reduction of Payment Due to Defects?
- What is Set-Off?
- What Must a Withholding Notice State?
- Is a Withholding Notice Required to Reduce the Price for Defects?
- Can a Purchaser Set-Off from Payments Due on One Contract Sums Recoverable on Another?
- 3.4 Payment for Variations
- When is the Purchaser Entitled to Vary the Works?
- How Are Variations Valued?
- How is Omitted Work to be Valued?
- Is a Contractor Quotation for Extra Work Binding if Accepted?
- 3.5 Claims for Additional Payment
- What is The Measure of Damages for Breach of Contract?
- What is The Third Party Rule?
- What Are Collateral Warranties?
- What Exceptions are There to the Third Party Rule?
- What is the Effect of the Contracts (Rights of Third Parties) ACT 1999?
- Is a Settled Final Account Binding?
- What is The Relevance of Settlement of SubContractor Claims in the Measure of Contractor’s Damages for Breach of Contract?
- Can a Contractor Recover the Cost of Preparing a Claim?
- If the Contractor Fails to give Notice of a Qualifying Event at the Right Time, Does He Have a Right to Payment?
- Can the Contractor Recover Damages From the Architect/Engineer for Failure to Administer the Contract Properly?
- 3.6 Remedies for Non-Payment
- Can the Contractor Recover Finance Charges and Interest for Late Payment?
- What is the Effect of the Late Payment of Commercial Debts (Interest) Act 1998?
- Where an A/E Under Certifies, is the Contractor entitled to Interest?
- Can the Contractor Suspend Performance for Failure to Pay?
- Does the Contractor Lose the SubContract Discount on Late Payment?
|
|