Daniel Atkinson Limited Alternative Dispute Resolution
Email:daniel@atkinson-law.com 7 Oakland Drive, Robertsbridge, East Sussex TN32 5EX England
Mobile: 07778 347 777 Tel: +44 (0) 1580 880 532 Fax: +44 (0) 1580 881 140

 

Adjudication
Carillion Construction Ltd v Devonport Royal Dockyard Ltd [2002] TCC

© Daniel Atkinson 21 August 2004


KEYWORDS: Carillion Construction Ltd v Devonport Royal Dockyard Ltd [2003] BLR79, Cruden Construction Ltd v Commission for the New Towns [1995] 2LLRep387, Ellerine Bros (Pty) Ltd v Klinger [1982] WLR1375, Grovedeck Ltd v Capital Demolition Ltd [2000] BLR181, Project Consultancy Group v The Trustees of the Gray Trust [1999] BLR377, RG Carter Ltd v Edmund Nuttall Ltd [2000], RJT Consulting Engineers Ltd v DM Engineering [2002] BLR217, Tradax International SA v Cerrahogullari TAS [1981] 2LLRep169, Housing Grants Construction and Regeneration Act 1996, Section 107, Section 107(2)(c), Section 107(3), oral variation, cost reimbursable, variations pursuant to contract, radical change, oral agreement, evidence in writing, dispute, implied terms, jurisdiction, His Honour Judge Bowsher.

In Carillion Construction Ltd v Devonport Royal Dockyard Ltd [2002] Judge Bowsher considered two issues.  The first issue was whether Section 107 of the 1996 Act and particularly Sections 107(2)(c) and 107 (3) and the requirement for contracts to be in writing, limited the jurisdiction of an adjudicator to consider a contract varied by oral agreement.  He distinguished variations under a contract from radical/fundamental changes to the contract.  The second issue was the meaning of "dispute" in adjudication.  Judge Bowsher based his decision on arbitration cases.

Background

Devonport owned and occupied Devonport Royal Dockyard. In 1997 the Ministry of Defence engaged Devonport, effectively as a main contractor, to upgrade the dockyard.

Devonport retained Carillion as subcontractor to upgrade No. 9 dock and provide new buildings with associated infrastructure. The contract was contained in two documents, a form of Sub-Contract Agreement and an Alliance Agreement, both dated the 10th March 1999 with a target cost payment mechanism and a "Gainshare" arrangement..

Carillion proceeded with their work, but the cost went substantially above the Target Cost and the Target Cost was amended six times between September 2000 and December 2001 up to 100 million.

A meeting of the Alliance Board took place on the 30th October 2001 to revise the payment mechanism. Carillion stated that at that meeting there was a binding oral agreement changing the payment mechanism to cost reimbursable without the "Gainshare". The parties could not agree on the fee but did agree to leave it to the Star Chamber, to which differences were to be brought. The Star Chamber did not agree on the level of fee to be allowed and it was never agreed.

After the alleged oral agreement Carillion submitted its Application No. 33 on the 16th April 2002 to Devonport in respect of Costs and Fee following achievement of Milestone 33 of 121,522,511.29.

Devonport questioned the application and no payment was made, although on earlier applications Devonport had paid 110 million.

Carillion gave notice of adjudication on the 6th August 2002 seeking the sum outstanding on Application No. 33.

The adjudicator was appointed on the 12th August 2002. The adjudicator issued his decision on the 24th September 2002 deciding that 

  1. a binding agreement was concluded on the 30th October 2001, that the project would become cost reimbursable;
  2. Devonport should pay 7,451,320, plus VAT, within 18 days;
  3. Devonport should pay the Adjudicator's fees.

The Adjudicators decision was not honoured. 

The Issues

Carillion applied for summary judgment before Judge Bowsher in the amount awarded by the Adjudicator. Devonport applied for summary judgment on their counterclaim and for declarations that 

  1. no relevant construction contract was concluded between the parties within the meaning of and for the purposes of Sections 107 and 108 of the Act;
  2. no relevant or adjudicable dispute was in existence between the parties at the date of the Notice of Adjudication;
  3. the provisions of the Act 1996 and the Scheme were not applicable to the Primary Claim made by Carillion.

The agreement between the parties contained no provision for adjudication, and so if there was any provision for adjudication it was under the Scheme.  Devonport submitted that the Adjudicator did not have power to decide his own jurisdiction and the question whether there was an oral agreement was a step in deciding his jurisdiction, though not decisive. Devonport contended that the Adjudicator's decision was not binding because the adjudicator had no jurisdiction to make it.

There were therefore two issues to be decided by Judge Bowsher

  1. The Alleged Oral Agreement:
    1. whether an oral agreement that varied the term of a written construction contract was required to be made or evidenced in writing, to give a statutorily appointed adjudicator jurisdiction to determine any dispute relative to that oral agreement, including the existence of such an agreement and any claim said to arise pursuant to that oral agreement.
    2. whether the alleged oral agreement was made or evidenced in writing, irrespective of whether an oral agreement was in fact concluded between the parties. 
  2. The Existence of a Dispute - whether a relevant or adjudicable dispute in relation to the claim sought to be enforced had arisen by the 6th August 2002, the date of Carillion's notice of adjudication..

Issue 1 - the Alleged Oral Agreement

The dispute about the meeting of the 30th October 2001 was that

  1. Carillion stated that it was agreed that their costs would be reimbursable with the issue of the fee to be referred to the Star Chamber, and 
  2. Devonport stated that it was agreed that cost reimbursable would be recommended to the Star Chamber, leaving it to the Star Chamber to decide.

Judge Bowsher found that the documents to which he had been referred:

  1. evidenced the fact that there was a discussion whether the contract should become cost reimbursable and about the fee;
  2. did not evidence that there was an oral contract made in any terms because the documents were conflicting, so the documents did not even indicate the existence of an unconditional contract;
  3. did not evidence any agreement as to the definition of "cost reimbursable";
  4. did not evidence any agreement about the fee. 

Judge Bowsher observed that by Section 107, for the purposes of the relevant part of the Act a construction agreement must be in writing.  

In order to decide the issue, Judge Bowsher assumed that there were an oral agreement to the effect found by the adjudicator, and asked would it be, within the meaning of the Act, an agreement in writing? He observed that Section 107 provided that an oral agreement may be treated as an agreement in writing

  1. if the agreement is evidenced in writing (s.107(2)(c)); or
  2. where parties agree otherwise than in writing by reference to terms that are in writing, they make an agreement in writing (s.107(3)). 

Judge Bowsher held that the judgment by the Court of Appeal in RJT Consulting v. D.M. Engineering [2002] BLR 217 was authority for the following propositions:

  1.  a contract is not evidenced in writing merely because there are documents which indicate the existence of a contract; per Ward and Walker L.J.J.
  2. all the terms of the oral agreement must be evidenced in writing; per Ward and Walker L.J.J.
  3. the material terms of the agreement must be evidenced in writing; per Auld L.J.J.

Judge Bowsher observed that the judgment of Auld L.J. differred in terms from the judgments of Ward and Walker L.J.J., but it was unnecessary to consider whether Auld L.J. was actually differing from his brother judges or merely explaining and elaborating on what they said. The difference, if any, was immaterial for the instant cae. The whole point of the alleged agreement was that the contract would become cost reimbursable. Judge Bowsher held crucially that within the context of Auld L.J's judgment, it was a material term and therefore must be evidenced in writing. 

Judge Bowsher referred to Grovedeck Ltd. v. Capital Demolition Ltd. [2000] BLR181, which he observed was approved by both Ward L.J. and Walker L.J. in  RJT Consulting v. D.M. Engineering [2002] in which it was held that disputes as to the terms, express and implied, of oral construction agreements were not readily susceptible of resolution by a summary procedure such as adjudication and Parliament intended that such disputes should not be determined by Adjudicators under the Act.

Judge Bowsher referred to the judgment of Walker L.J. in RJT Consulting v. D.M. Engineering [2002] in which he held that it was inappropriate for an Adjudicator to have to deal with the disputes which arose as to the terms of an oral contract. 

Judge Bowsher held that these considerations were particularly important in the instant case where the adjudicator formed a view about the disputed oral agreement vital to his decision on the basis of conflicting documents without hearing oral evidence though, in fairness to him, the parties had agreed that there should be no hearing. 

Judge Bowsher held that the agreement found by the adjudicator was not evidenced in writing within the meaning of s.107(2)(c).

Judge Bowsher then turned to consider s.107(3) which provides that where parties agree otherwise than in writing by reference to terms that are in writing they make an agreement in writing.  Judge Bowsher held that Section 107(3) had to be read in conjunction with the whole of the first section of s.107(1) of the Act which stated that the provisions of that Part applied only where the construction contract was in writing, and any other agreement between the parties as to any matter was effective for the purposes of this Part only if in writing.

Judge Bowsher was unsure what situation was envisaged by s.107(3), unless it be a rare situation where party A approaches party B with a draft written agreement containing all the vital terms, they read it, and then shake hands on it as an agreed deal.  He observed that seemed to be covered by s.107(2)(a).  Judge Bowsher held that the Act did not provide for adjudication in relation to an alleged fundamental variation of a construction contract made orally and without writing. Any contention to the contrary was directly inconsistent with s.107(1) of the Act. 

Carillion relied upon the judgment of Judge Thornton in R G Carter Ltd. v. Edmund Nuttall Ltd  21st June 2000 

"Thus so long as it is either established or agreed that there is a contract in existence between the parties, that it is a construction contract ... any other dispute as to the terms of the construction contract is as much a dispute arising under the contract as would be a dispute as to the working through of any terms as to the valuation machinery."

The Court of Appeal in RJT Consulting v. D.M. Engineering [2002] supported that judgment stating that 

"Once jurisdiction to refer the matter to arbitration was established the Judge held, and in my judgment rightly held, that it was proper within that adjudication to decide whether or not a particular term had been incorporated into the contract. The scheme would be emasculated if a party were able to deprive the Adjudicator of his power to decide simply by putting up an argument that some term was or was not incorporated into an agreement that otherwise was accepted to be in writing."

Judge Bowsher observed that once a construction agreement in writing was before an adjudicator he had the jurisdiction to construe its express terms and to decide what, if any, terms were to be implied or incorporated by reference. He held that it was quite different to suggest that once a construction agreement was before an adjudicator he had jurisdiction to decide on the existence of an oral agreement not evidenced in writing just because it followed and amended the written agreement.

Judge Bowsher held that the oral agreement did not come under the heading referred to in the construction industry as "Variations made pursuant to a term of the contract". He held that what was in issue was an alleged oral agreement that radically changed the written agreement (if it was made). Judge Bowsher held that the citations from the judgments of Judge Thornton and the Court of Appeal were not intended to and did not apply to the sort of agreement in the instant case. Judge Bowsher held that the adjudicator did not have jurisdiction to enter on the adjudication. 

Judge Bowsher expressed no view as to whether there was or was not an oral agreement in the terms alleged. To determine that question required oral evidence and cross-examination.

Issue 2 - Dispute

The next issue on jurisdiction was whether a relevant or adjudicable dispute in relation to the claim sought to be enforced had arisen by the 6th August 2002, the date of Carillion's notice of adjudication.

Judge Bowsher considered that whatever his final decision on this point, it would not affect the overall result having regard to the finding he had already made on lack of jurisdiction.

Devonport argued that although there had been a refusal to pay on Application 33, subject to the giving of further information, it was not until the 25th July 2002 that Carillion put forward anything like the basis on which they claimed in the adjudication, and on the 1st August 2002 Devonport asked for further information that was not given before the notice of adjudication. Until that information was given Carillion could not know whether or what to pay. Carillion, it was said, served its notice on the 6th August 2002 without providing the clarification, information and time requested by Devonport, and therefore without affording Devonport any proper opportunity of considering and accepting or rejecting the claims first made on the 5th July 2002.

Judge Bowsher referred to the judgment in Ellerine Bros. (Pty.) Ltd. v. Klinger [1982] 1 W.L.R.1375 at 1381where Lord Justice Templeman said, in reference to s.1(1) of the Arbitration Act 1975 

"...  if letters are written by the plaintiff making some request or some demand and the defendant does not reply, then there is a dispute. It is not necessary for a dispute to arise that the defendant should write back and say 'I don't agree'. If on analysis what the plaintiff is asking or demanding involves a matter on which agreement has not been reached and which falls fairly and squarely within the terms of the arbitration agreement, then the applicant is entitled to insist on arbitration instead of litigation."

 Then at p.1383 Lord Justice Templeman quoted the statement of Mr. Justice Kerr in Tradax International S.A. v. Cerrahogullari T.A.S [1981] 2 Ll.Rep.169 at 163, and said 

"... as I understand it, the judge is saying--and I agree--that silence does not mean consent. If you can point as was the case in London & North Western & Great Western Joint Railway Cos. v. J.H. Billington Limited [1899] A.C.79, to an express or implied agreement to pay a particular sum then there is no dispute and the action can proceed. But the fact that the