In Bloor Construction (UK)Limited v Bowmer & Kirkland (London)
Limited (2000) TCC the issue was whether the adjudicator could alter his
own decision to correct a clerical mistake or error arising from an
accidental slip or omission, and if so in what circumstances.
Bowmer as main contractors entered into a contract with Bloor as
subcontractors under which Bloor was to undertake labour and plant
groundworks (including sub-structure, drainage, groundfloor slabs and
external works) for a development at Whitely village, Fareham in Hampshire.
The main contract was in the JCT standard form 1980 edition incorporating
amendments issues in April 1998 to comply with the 1996 Act. Clause 41A.5.3
required the Adjudicator reach his decision within 28 days of his receipt of
the referral and "forthwith send that decision in writing to the
parties". The parties agreed that on the facts, the Adjudicator was
required to reach his decision by the end of 9th February 2000.
At a meeting on 4th February 2000 between the parties and the
Adjudicator, the Adjudicator stated that he would reach his decision in
principle on 9th February 2000 and communicate it to the parties
on 11th February 2000, allowing himself a short period to
complete his calculations and to finalise his decision for publication. On
11th February 2000 the Adjudicator sent a fax to both parties
containing a covering letter and his decision.
It was held by His Honour Judge Toulmin CMG QC that in the absence of
consent to an extension of time by the party referring the dispute, the
decision was rendered out of time. Although it is not clear from the
decision why the main contract terms were relevant in this case, it was held
that "forthwith" in Clause 41A.5.3 meant what it said and
required that the process of communicating the decision should be started
immediately after the decision had been reached. The decision has two
elements; first, reaching the decision and, secondly, sending that decision
to the parties. If the decision was sent only by post, it would not be
received immediately. In this case neither party dissented from the
Adjudicators proposal to publish his decision on 11th February
2000 and this was rightly taken to signify that both parties agreed to this
short extension of time.
The adjudicators decision failed to take into account payments made on
account by Bowmer. The error was pointed out to the Adjudicator by Bowmer
who sent a corrected decision by fax on 11th February 2000,
without inviting submissions from Bloor.
Bloor argued that once the Adjudicator has communicated his decision to
the parties, his duty is at an end and he has no power to correct any
errors, except perhaps clerical errors. Parliament laid down a quick and
certain interim procedure for resolving disputes on the basis that any
temporary injustice can be corrected at a later date. The Adjudicator has a
semi-judicial role which terminates at the delivery of his decision.
It was held that the Act and the Scheme do not address the question of
whether and, if so, in what circumstances a decision once taken can be
amended. It is solely a matter of contract and in this case the agreement
between the parties was silent. The question therefore was whether or not
terms could be implied under which an Adjudicator can amend his decision.
Reference was made to Section 57 of the Arbitration Act 1996, which in
the absence of agreement between the parties allowed the Arbitrator to
correct an award so as to remove any clerical mistake or error arising from
an accidental slip or omission, or clarify any ambiguity in the award.
Reference was also made to decided cases on what amounts to an accidental
slip or omission - The Montan (1985) 1Lloyds 189 CA, R v Cripps
(1984) 1QB 686 and King v Thomas McKenna Limited (1991) 1AllER653.
It was held that in the absence of a specific agreement by the parties to
the contrary, there is to be implied into the agreement for adjudication the
power of the adjudicator to correct an error arising from an accidental slip
or omission or to clarify or remove any ambiguity in the decision which he
has reached, provided this is done within a reasonable time and without
prejudicing the other party. The adjudicator may exercise the power on his
own initiative or on the application of a party. One further reason for such
a power is that the High court does not have the ability to correct obvious
errors in adjudication except in very restricted circumstances, even where
such errors cause manifest injustice.
In the instant case it was held that the error was one that could be
corrected by the Adjudicator. It appears from the decision that the
adjudicator must give the parties a reasonable opportunity to make a
presentation to the adjudicator. Judge Toulmin was prepared to hear argument
as to whether further opportunity should be given to Bloor to make
representations to the Adjudicator,but in fact no further submissions were
made.
|