Atkinson Law
Article |
|
Published Date:
22 April 2007 |
Architect's Duty of Inspection.
© Daniel Atkinson 2007 22 April 2007
In Ian McGlinn v
Waltham Contractors Ltd [2007] EWHC149(TCC)
,
His Honour Judge Peter Coulson dealt with a wide range
of legal issues. In doing so he examined the Architect's duties of
inspection which will be of interest to all architects engaged on building
contracts under the modern forms of contract.
The particular building project related to a luxury house called "Maison d'Or"
that was built for the multi-millionaire Mr Ian McGlinn in Jersey between January 1999 and
December 2001. It sat empty for the next 3 years whilst the alleged
deficiencies in its design and construction were investigated by a team of
experts and contractors. In 2005 it was completely demolished and not
rebuilt. McGlinn's primary case was a claim for damages of £3,649,481.34.
McGlinn's case was that Maison d'Or was so badly designed, and so badly
built, that he was entitled to demolish it and start again. He claimed
damages for breach of contract/negligence against the building contractors,
Waltham; the architects, Huw Thomas Associates ("HTA"); the structural,
mechanical and electrical engineers, the quantity surveyors and so-called
Project Managers.
Coulson J found that the project was not set up in either an appropriate
or a conventional way. There was no overall co-ordination of the contract,
no ordinary contract documentation and no clear chain of command either on
or off-site. There was no lead consultant in the conventional sense.
The building project was not therefore conventional in any sense. It could
not be assumed that a consultant was responsible for a particular function
simply because the obligation was one which a professional of the respective
disciplines might usually take on.
There was no claim against HTA in relation to pre-contract advice or the
administration of the building contract between the employer McGlinn and the
contractor Waltham. The claim against HTA concerned the absence of a
specification and the failure to inspect.
There was confusion over HTA's terms of appointment. Coulson J held that
the appointment was to carry out the Work Stages identified in a document
sent by HTA to McGlinn on 12 August 1997, save where it was clear from the
evidence that the services were not required or were to be provided by
others. That document was the "Architect's Appointment" documentation
first produced by RIBA in 1982 and subsequently updated in 1990.
Although superseded at the time by SFA/92 (Standard Form of Agreement for
the Appointment of an Architect), the extracts sent were based on the
earlier document.
The Absence of a Specification
Work Stage C of the Architect's Appointment required the architect to
prepare outline proposals and Work Stage D required the architect to develop
a scheme design. Work Stage E required the architect to develop that scheme
design and to obtain the client's approval of the type of construction,
quality of materials and standard of workmanship to be provided by the
contractor. Work Stages F and G required the architect to prepare production
information including drawings, schedules and specification of materials and
workmanship and to provide information for the Bills of Quantities.
HTA through its regular invoices indicated that it had undertaken all
these Work Stages. There was no other professional who could possibly have
produced most of these documents. The outline proposal, the scheme design,
the detail design, and the preparation, under Work Stages F and G, of
drawings, schedules and a specification of materials and workmanship, were
all for HTA to produce.
It was held that HTA was obliged to provide a specification in respect of
these works and failed to provide such a basic document, which was a major
failing on the part of HTA.
Quality Standards
It was clear that the luxury house had to be completed to the highest
standard. Mr McGlinn wanted the finishes to have the same look as a
luxury yacht, but that did not seem to have been conveyed to the consultants
and contractor, and therefore it affected progress and payment.
It was held that HTA's obligation to produce a design and inspection
service with the aim of producing a very high quality finished building did
not extend to the production of a perfect building.
Coulson J stated that the obligation did not extend to the "boat
standard". The evidence before Coulson J was that a perfect standard of
interior fitting and finish could only be provided by boat-fitting
specialists, not construction contractors. Neither HTA, nor any of the other
consultants, had made any such arrangements, which indicated that they did
not understand that a perfect standard was required. Such a standard was
unusual. It was found that at no time did Mr McGlinn require HTA, DJH or WL
to produce or work to the boat standard, as opposed to a very high standard
of finish.
There was no specification which set out the high standard. HTA
therefore failed to spell out to Waltham the very high standard required by
McGlinn. The absence of a specification emphasised the importance of HTA's
periodic inspections. They were the only way in practice in which HTA
intended to get across to Waltham the standard required.
Design
Coulson J held that HTA was not responsible for the detailed structural
design, the detailed M&E design, and the detailed design of the interiors
and finishes. They were, however, responsible for the co-ordination of those
three aspects of the design with their own work.
If there was a clash between any of those three aspects of the design,
and HTA's own design work, then HTA had both to point out the clash and,
perhaps in conjunction with the other professional involved, they had to
endeavour to find a way to resolve it. This task was particularly important
in relation to the interiors/finishes. They were obliged to carry out their
own design work, and their co-ordination role, exercising reasonable skill
and care.
The Principles of Law on the Obligation to
Periodically Inspect
Coulson J referred to Sutcliffe v Chippendale & Edmondson [1971]
18 BLR 149 in relation to an architect's obligations to his client once work
started and particularly the obligation to supervise. He observed that
the obligation to supervise under the old RIBA forms had now gone under
modern forms and there was only the obligation to make periodic inspections
He reviewed the sparse caselaw and provided a summary of the applicable
principles.
- The frequency and duration of inspections should be tailored to the
nature of the works going on at site from time to time: see Corfield v
Grant [1992] 29ConLR58. It was not enough for the inspecting
professional religiously to carry out an inspection of the work either
before or after the fortnightly or monthly site meetings, and not
otherwise.
- Depending on the importance of the particular element or stage of the
works, the inspecting professional could instruct the contractor not to
cover up the relevant elements of the work until they had been inspected:
see Florida Hotels Pty Ltd v Mayo [1965] 113 C.L.R. 588. If the
inspecting officer was carrying out inspections which were tailored to the
nature of the works proceeding on site at any particular time, he will
have timed his inspections in such a manner as to avoid affecting the
progress of those works.
- The mere fact that defective work is carried out and covered up
between inspections will not automatically amount to a defence to an
alleged failure on the part of the architect to carry out proper
inspections; that will depend on a variety of matters, including the
inspecting officer's reasonable contemplation of what was being carried
out on site at the time, the importance of the element of work in
question, and the confidence that the architect may have in the
contractor's overall competence: see Sutcliffe v Chippendale &
Edmondson [1971] 18 BLR 149.
- If the element of the work is important because it is going to be
repeated throughout one significant part of the building, such as the
construction of a proprietary product or the achievement of a particular
standard of finish to one element of the work common to every room, then
the inspecting professional should ensure that he has seen that element of
the work in the early course of construction/assembly so as to form a view
as to the contractor's ability to carry out that particular task: see
George Fischer Holdings Ltd v Multi Design Consultants Ltd
[1998]ConLR85.
- Reasonable examination of the works did not require the inspector to
go into every matter in detail; inevitably some defects would escape his
notice: see East Ham Corporation v Bernard Sunley [1966] AC 406.
- The architect does not guarantee that his inspection will reveal or
prevent all defective work: see Corfield v Grant [1992] 29ConLR58.
It was not appropriate to judge an architect's performance by the result
achieved.
Applications of the Principles
Coulson J applied the above principles generally to HTA's performance and
in addition to specific alleged defects to establish the extent of any HTA
liability. Only the general application is considered here.
It was held that HTA was obliged to inspect the works being constructed
to its design in accordance with these principles. In respect of the
structural works and the M&E works, HTA's obligation to inspect was more
limited. It extended to ensuring that any co-ordination issues had been
properly dealt with by Waltham, and it might possibly extend to any very
obvious errors in the construction of these elements. HTA did not have
the same inspection obligation in respect of a detailed element of the work
designed by the engineer, as for an element of the work which they
themselves designed. HTA were obliged to carry out periodic inspections in
respect of the interior/finishes notwithstanding other consultant's primary
design obligations.
As to HTA's administrative functions HTA was obliged to point out to the
quantity surveyors, particular elements of defective work, depending on
their significance or importance. In the circumstances of this case, walking
round the site after the site meeting accompanied by the quantity surveyor
pointing out areas of defective work that the contractor was required to put
right, was a generally sufficient approach.
Monthly inspections on the same day as the monthly meeting during the
critical period of construction of the main structure was insufficient.
Monthly visits, telegraphed in advance, was an inadequate performance of the
inspection function.
The complete absence of any records by HTA of the inspections identifying
the defects and what was to be done was unsatisfactory.
It was a mistake that HTA left the oversee of the project to someone who
was not a partner in, nor associate of HTA.
Snagging
Coulson J recognised the usual practice in the UK construction industry
for the contractor to hand the building over to the architect for snagging
purposes, when a building is nearing completion. The architect then
undertakes his own careful inspection of the building and records, in a
detailed snagging list, all those items which he considers to be patently
incomplete or defective. The contractor is then required to correct all the
items on the snagging list. Once the architect is satisfied that all the
items on the snagging list have been corrected, then, unless some other
event has intervened, the architect will normally issue a certificate of
Practical Completion.
Coulson held that if during an inspection prior to handover/snagging, the
architect identified defective work he was obliged to point it out to the
contractor and require it to be remedied. The reason for this was that if
circumstances unexpectedly brought the contract to a premature end before
such defects had been remedied and had been accounted for in the interim
certificates, there would be a consequential over-payment which might be
irrecoverable from the contractor. Also it was better to deal with defective
work as the works were progressed, rather than at the end.
Coulson recognised that there would be other matters, particularly
concerned with final finishes, which not only could be left until formal
handover and snagging, but which it was sensible and productive to leave
until that stage. Coulson referred to and adopted the views of Mr Recorder
Reese QC in Oval (717) Ltd v Aegon Insurance Co (UK) Ltd [1997]
54ConLR that an employer did not expect initial perfection in on-site
performance by all operatives engaged in the works at all times. Temporary
disconformities would not constitute either non-performance or
non-observance of the terms of the construction contract. Coulson held that
if an item has been left incomplete when a contract came prematurely to an
end, the question was whether it was something which the contractor (or the
architect) might fairly have regarded as work in progress, or whether it was
something which should properly have been treated as complete. In some cases
it would be counter-productive for the inspecting officer repeatedly to
point out purported defects in work that was still in the process of being
carried out.
Conclusions
The architect's obligation to inspect is not onerous, but does require
the architect to carefully consider the project on which he has been engaged
and to change his inspection pattern to take into account the importance of
the stage of construction. This is a matter of experience, and such a
role of inspection should not be left solely to someone who is not a partner
or an associate. Proper records should be kept of the inspections and
of the work required to be carried out. Any defects should be taken
into account in interim certificates.
|