NEC3
Article 2 |
|
Published Date:
03 Feb 2008 |
NEC3 Formality & Contract Formation
© Daniel Atkinson 2008 03 February 2008
Construction Practice
The creation of a
contract is a non-confrontational step. The parties are free to agree how
they will conduct and complete the joint enterprise which is the subject of
the contract.
The freedom of contract
extends to the procedure and manner in which the decision is taken for work
to proceed. Many construction projects proceed with no formality and with
little regard to the terms of the contract. The following are examples of
common practices in the construction industry.
- Not infrequently the
employer simply requests the contractor to carry out work and the
contractor’s response is to immediately start on site. There is no
discussion on terms of the contract and even on price for the work.
- On a small building
project the builder may state a price for the building work and the owner
requests him to proceed to do the work, with no discussion on the terms of
contract or by a simple reference to a standard form of contract.
- More often the employer
and contractor may exchange communications in writing setting out matters of
specification, programme and payment. The terms of the contract will
usually be by reference to a standard form with a list of amendments. A
common procedure is for the employer to issue tender documents, followed
frequently by amendments and clarification of matters raised by the
bidders. The contractor completes the tender adding additional
documentation which he submits as his bid for the work. The contractor may
qualify his bid or suggest alternative design or programmes to the tender.
Communications and meetings may follow seeking clarification and in some
cases modification of the bid. Frequently the decision to proceed is made
in a meeting following discussion.
- During discussions on
the main works the need for an early start to achieve completion may result
in the contractor starting part of the work on site on a simple request or
letter, even though discussions on the main works have not been completed.
As discussions continue or difficulties arise in concluding the main
contract, the contractor may be requested to carry out greater parts of the
works. At each stage reference may be made to the intended main contract
terms which are not concluded. The project may even be administered
following the procedure in the referred unconcluded main contract terms.
- Subcontracts are a
common feature of construction projects. It is common practice for the
contractor to invite bids from subcontractors making reference to the main
contract and his own conditions of contract or to a standard form with his
own amendments. The invitation is usually a proforma which is required to
be completed by the subcontractor. The subcontractor submits his bid often
omitting to provide the information requested by the contractor and making
reference to his own conditions of contract or another standard form.
Contractors will often hold meetings with the subcontractor to clarify the
bid and negotiate its terms. The contractor may then issue a subcontract
order which may or may not record any agreement. Frequently the
subcontractor will have commenced work on the project whilst discussions are
still proceeding.
Each of the above
examples of practice in the construction industry may cause difficulties.
If the parties’ agreement is wholly oral or partly oral and partly in
writing, then it may be difficult to establish the oral statements. It may
be difficult to determine which of the many documents were intended to be
part of the agreement.
In order to achieve
commercial certainty good commercial management requires that there should
be some formality which defines the formation of a contract and which allows
the terms of the contract to be identified. The formality should be a
procedure which reduces the terms of the contract wholly to writing. This
is the best practice procedure which is evident from the standard forms of
contract. Many standard forms of contract are drafted on the basis that any
contract is to be wholly in writing and imply a manner in which a contract
is to be made.
If the procedure for
formation of contract stated or implied in a standard form is not followed,
this does not mean that the terms of the standard form may not be the terms
of the construction contract. For instance, in the case of a contract such
as FIDIC which incorporates a Form of Agreement a contract can be made other
than by the formal signing of the Form of Agreement. Depending on the facts
the contract could be made by a sufficiently clear oral acceptance of an
appropriate written proposal Ove Arup & Partners International Ltd v
Mirant Asia-Pacific Construction (Hong Kong) Ltd [2003]CA [2004]1 BLR 49
In the examples above
of the practice in the construction industry, the parties may simply refer
to the standard form with the intention of incorporating its terms in any
concluded contract.
If a procedure for
formality is not followed, then it will be necessary to examine all the
correspondence and the circumstances to determine whether or not a contract
has been made and if so its terms.
The Legal Requirement for Formality
The requirement of
formality may prevent a contract being formed. First, a particular
formality may be required by law because of the the type of transaction or
because of the status of one or both parties. Second, any or all the
parties may make clear that unless a particular formality is adopted then no
contract can be concluded.
There is no general
rule in English Law that a contract should be made in a certain form. There
are exceptions, which now all depend upon statutes which deal with specific
types of contracts, particularly relating to transactions in land and for
guarantees which require the formality of writing.
A construction contract
will not usually involve a transaction in land. The contractor is simply
granted a licence for the use of or possession of the site for the period of
construction, and no lease or sale of land is involved. A construction
contract therefore will not usually need to be in writing.
It is common in
construction projects for the employer to require the contractor to procure
a guarantee in the form of a bond in the employer’s favour for the
contractor’s performance. Since the bond is often procured after formation
of the main contract, the bond is not only required to be in writing but
also in the form of a deed, since there will be no consideration for the
bond.
A deed was formerly
always a document executed under seal. Following the Law of Property
(Miscellaneous Provisions) Act 1989 S1(1)(b) this no longer applies to
deeds executed by individuals, for which a seal is no longer required. The
formality required for a deed executed by an individual is that it is signed
in the presence of a witness who attests the signature and that it is
described or expressed to be executed as a deed. The formality required of
a deed by a company is now found in S.36A of the Companies Act 1985,
having been amended by S.130 of the Companies Act 1989. S.36A(3)
allows for execution by two directors or a director and secretary and for
the document to state it is a deed.
A deed extends the
right of action on a contract from 6 years on a simple contract to 12 years
from the date of the breach of contract. As a matter of interpretation of a
warranty deed the parties may intend and agree not to create an obligation
which lasts longer than the underlying obligation it supported but rather,
to create obligations and causes of action under the building contract
together with collateral obligations and causes of action under the warranty
deed, which crystallise simultaneously, and take effect by the same period
of time Northern Shell plc v John Laing Construction Ltd [2003] EWCA Civ
1035.
Since the usual longer
limitation period is perceived to be an advantage to an employer, many
construction contracts are required by employers to be executed as a deed
even though the formality is not required as a matter of law. In order to
ensure that the construction contract is executed in the form of a deed,
employer’s frequently include statements in tender documentation that unless
and until agreement is made in the form and manner exhibited in an attached
proforma, no contract can be concluded.
Even if the
construction contract is not required to be in the form of a deed, the
employer may specify that the procedure for formation of the contract shall
only be by signature of a written agreement. The advantages of certainty
leads many contractors to stipulate the requirement of the formality of
writing, particularly where there are extensive negotiations and numerous
technical documents and different versions of the proposed contract terms.
If a party is
consistent in its requirement for formality before a construction contract
can be concluded, then the failure to satisfy this requrement will prevent
the formation of a contract even if all terms have been agreed. A
distinction is made between an executory contract in which work has not yet
been carried out and an executed contract in which the work has been
completed. If the work has been commenced or carried out in accordance with
the agreement, despite the absence of the required formality, then this may
be evidence of a waiver of the formality and a contract may be implied on
those terms. Even then, if the parties continue to insist on formality in
clear terms then no contract will have been concluded The relevant
authorities for this principle of law are as follows:
- If a purported
acceptance is expressed to be `subject to contract', or some other words are
used which show that further negotiations or events are contemplated, there
is no concluded contract Cranleigh Precision Engineering Ltd v Bryant
[1965] 1 WLR 1293.
- Even if the parties
have reached agreement on all the terms of the proposed contract,
nevertheless they may intend that the contract shall not become binding
until some further condition has been fulfilled. That is the ordinary
"subject to contract" case Pagnan SpA v Feed Products Ltd [1987]2 Lloyds
Rep 601.
- If the project is an important one and it
was `commercially improbable' that the parties would commence the project
without concluding a formal contract, then there may be a concluded contract
despite the offer being expressed to be `subject to contract' Fraser
Williams (Southern) Ltd -v- Prudential Holborn (1992).
- Where a transaction has been performed on
both sides, it will often be unrealistic to argue that there was no
intention to enter into legal relations. The term “the
Contract will be executed as a deed under seal”
is a requirement that unless the contrary was either expressly agreed
between the parties or arose between them by necessary implication, any
contract would have to be under seal. There was
nothing to prevent the parties from agreeing to dispense with the
requirement for a contract under seal. If both
sides continue to refer to the preparation of or need for formal contract
documents and there is no evidence of waiver of the formality then there is
no concluded contract J. Jarvis & Sons plc v
Galliard Homes Ltd [1999]CA.
- In general, except in a
very strong and exceptional case, the effect of the words “subject to
contract” in an agreement prevents an executory contract from coming into
existence. The words are taken to mean that until a further contract has
been executed neither party is to owe the other any contractual obligation.
The agreement is not executory if the parties did those things that the
agreement contemplated that each should do for the benefit of the other. In
that case the parties are taken to have entered into an implied binding
contract on the terms of the agreement The Rugby Group Ltd v Proforce
Recruit Ltd [2005] EWHC 70 (QB) overturned on appeal but not on this
point.
Construction Industry Best Practice
The developed best
practice of the construction industry can be seen in the manner in which the
standard forms of contract define the term “contract” and assume the manner
in which the contract will be formed. The best practice evidenced by the
standard forms is first that the contract is reduced to writing, second that
it is identified by reference to listed documents and lastly that the date
of formation is marked by a signed agreement or by the exchange of
documents, such as a letter of acceptance.
- FIDIC Red Book 1stEdition 1999 is published
by the Federation Internationale des Ingenieurs-Conseils for use on building
and engineering works designed by the Employer and intended to be for
international application. The “Contract” is defined in terms of the
Contract Agreement, the Letter of Acceptance, the Letter of Tender, the
Conditions, the Specification, the Drawings, the Schedules and the further
documents listed in the Contract Agreement or the Letter of Acceptance. The
Contract Agreement is required to be executed within 28 days of the
Contractor receiving the Letter of Acceptance. The Form anticipates that
there may be no Letter of Acceptance but only a Contract Agreement and in
that case defines “Letter of Acceptance” as the Contract Agreement and the
date of receiving the Letter of Acceptance as the date of the Contract
Agreement.
- ICE 7thEdition Measurement Version
is published for and approved by the Institution of Civil Engineers, the
Association of Consulting Engineers and the Civil Engineering Contractor’s
Association and is used in connection with works of civil engineering
construction. The term “Contract” is defined as the Conditions of Contract,
Specification, Drawings, Bills of Quantities, the Form of Tender, the
written acceptance of the Form of Tender and if it has been completed the
Form of Agreement. The Form of Agreement is annexed to the Conditions and
the Contractor is required to execute the agreement if called upon to do so.
- IChemE 4thEdition 2001 Lump Sum (The
Red Book) is published by the Institution of Chemical Engineers and is used
for any process plant not only chemical processes. An Agreement is bound
into the standard form and at Article 1 the term “Contract” is defined by a
list of documents which include the Agreement. The Agreement is required to
be dated and is required to be signed by the Parties.
- JCT 2005 SBC/Q is published for the Joint
Contracts Tribunal Limited and is used extensively in the UK building
industry. An Agreement is bound into the standard form. The Agreement is
required to be dated and is required to be signed by the Parties. The
Contract Documents are defined in the Conditions as the Contract Drawings,
the Contract Bills, the Agreement, the Conditions together with where
applicable the Employer’s Requirements, the Contractor’s Proposals and the
CDP Analysis. The Contract Particulars attached to the Agreement are
required to be completed by the Employer
- MF1 (Rev 4) 2000
Edition is published by
for the Joint IMechE/IEE committee on Model Forms of General Conditions of
Contract by the Institution of Electrical Engineers and is used for the
supply and erection of electrical, electronic or mechanical plant. The
contract between the parties is defined in terms of a Tender and any agreed
amendments or variations and a Letter of Acceptance from the Purchaser.
NEC3 ECC and ECS Contracts
The NEC third edition
(“NEC3”) published Engineering Construction Contract (“ECC”) is a bound
document comprising the following parts:
- Schedule of Options;
- Core Clauses;
- Main Options A-F Clauses;
- Dispute Resolution Options W1 and W2;
- Secondary Options X1-7, X12-18, X20, Y(UK)2, Y(UK)3 and Z Clauses;
- Schedule of Cost Components;
- Shorter Schedule of Cost Components;
- Contract Data part one and part two proforma.
There are also separate
publications for each of the Main Options A-F which combine the Core Clauses
(“CC”) and Main Option Clauses (“MO”) for that Main Option together with the
other parts above.
The published Engineering Construction Subcontract (“ECS”) is a similar publication to the
ECC, but there are no separate publications for each Main Option.
ECC does not refer to
an agreement and there are no provisions which depend upon the execution of
an agreement. There is no express provision in the published ECC which
requires the method of formation of contract to be the completion and
signature of an agreement. The published documents do not imply that an
agreement is the only method of contract formation and do not limit the
creation of the contract to the completion and signature of an agreement.
As described above it
is possible for parties during their dealings to make creation of the
contract conditional on the formality of a completed signed agreement. The
employer may do so in the instructions to tenderers, or by separate letter
or even in the documents issued to the contractor. The contractor may also
stipulate the method of contract creation. The effect of such statements
preventing creation of a contract other than by the formality of execution
of an agreement will depend upon the circumstances.
ECC does not refer to a
tender or letter of acceptance. There is no express requirement in the
published ECC that the method of formation of the contract is to be by
exchange of written communications or the formality of written offer and
acceptance.
Although the ECC does
not address the method of formation of contract, there are numerous
references to the existence of a contract. The term “this contract” is used
throughout the published documents. There are numerous references to
actions which “this contract requires”. There is no express definition of
the term “contract” either in terms of a list of documents or a document
which includes a list of contract documents. There is no express statement
of the manner of creation and whether or not it is limited to exchange of
documents.
The definition of
“Contract Date” at ECC CC 11.2(4) refers to the date when “this contract”
came into existence, but there is no indication of the manner in which any
contract is to be created. The definition, without further detail, shows
that ECC was not intended to prescribe or limit the method of formation of
contract adopted by the Parties.
ECC Contract Data part
one proforma states that the data is to be provided by the employer and
provides italicised terms to be defined by completion of the proforma.
There is no statement or indication of the manner of creation of the
contract. The Contract Data part one is not specific to any contractor but
is intended to be issued as part of the invitation for tenders or bids.
There is for instance no identification of the contractor in the Contract
Data.
ECC Contract Data part
two proforma states that the data is to be provided by the contractor and
again provides italicised terms to be defined by completion of the proforma.
The Contract Data part two is intended to be an offer, tender or bid by the
contractor. There is no statement or indication that a contract cannot be
made by simple acceptance of the offer, either orally or in writing.
The ECC does no require
a contract to be created in a particular manner. There is no express
provision in the published ECC preventing the method of formation of the
contract being by by oral communication or by conduct or performance.
The published ECC does
not include guidance notes, but a separate document entitled “guidance
notes” is published which states that one of the purposes is to provide
guidance on how to use the ECC. The guidance includes statements on the
creation of a contract based on ECC. The guidance notes confirm the above
conclusion that there is no intended formality for creation of the contract.
- The guidance notes
state that frequently negotiations are necessary to clarify intentions or
agree amendments.
- The guidance notes
state that the contract can be created by acceptance of a tender or revised
tender, but does not state how that may be achieved. A suggested form of
agreement is attached at Appendix 3, but as stated in the guidance notes
that records the agreement already made. The proforma agreement lists the
documents forming part of the agreement which includes a letter of
acceptance. There is also provision for listing other documents which form
part of the agreement.
The above conclusions
in relation to ECC apply equally to ECS and the creation of the subcontract
between contractor and subcontractor mutatis mutandis.
|