Yorkshire Water Authority v Sir Alfred McAlpine Ltd 32BLR119 (1985)
© Daniel Atkinson 2000
KEYWORDS: |
Law, free legal information, cases, article, ICE standard form, clause 13, clause 51, clause 52,
specified method of working, impossibility, variation, |
The contract involved the construction
of an outlet tunnel by a specified method. The Engineer under an ICE form had not accepted that there was a
specified method statement and therefore the appropriate instructions under Clause 13 -
orders under Clause 51 - had not been given. There had been a long delay following which
the tunnel was constructed by the Contractor by a different method to that specified. The
question to be answered was whether the contractor was entitled to a variation order under
Clause 51(1) if the arbitrator comes to the conclusion that it was impossible to follow
the method statement incorporated in the contract and that changes in the specified
sequence, method or timing of the works were necessary for the completion of the works. It
was held that there was a specified sequence or method of construction and the contractor
was entitled to a variation order with the consequent entitlement to payment of the value
of such variation as is provided in Clause 51(2) and Clause 52.
|