|
THE JCT standard forms of contract prescribe many types of notices
and certificates, the inter-relation of which can lead to disputes,
particularly in relation to liquidated damages.
Liquidated damages clauses avert the legal hurdles of proving
actual loss as a result of a breach of contract. They benefit the
contractor since he knows his level of liability for a particular
risk and they benefit the employer through reduced bids.
The clauses of the JCT forms provide a code for the payment of
liquidated damages. The period for which liquidated damages can be
claimed will be known to the employer once the completion date and
the date of practical completion has been determined.
If the contractor fails to complete by the completion date then
three conditions have to be satisfied before the employer has the
right to deduct liquidated damages. They are:
The architect must issue a non-completion certificate.
The employer must give a general notice that he might deduct
liquidated damages.
The employer must issue a withholding notice against each interim
certificate for payment stating the amount of liquidated damages he
intends to deduct from the sum due.
In A Bell and Son (Paddington) v CBF Residential Care and Housing
Association [1989] the court held that the employer lost the right
to deduct liquidated damages because the requirement that an
architect's non-completion certificate be issued had not been
fulfilled.
The architect had granted an extension of time that cancelled the
previous non-completion certificate under the JCT 80 form and he had
not issued a replacement certificate.
In J F Finnegan v Community Housing [1993] the Court of Appeal
held that a written notice from the employer under JCT80 is a
condition precedent to the right to deduct liquidated damages. The JCT forms have been revised to take into account these decisions.
The revised forms are JCT 1998 and JCT 2005. The terms of the 1998
form have been considered by the Court of Appeal in Reinwood v L
Brown & Sons.
The key date was January 25, 2006, the final date for payment of
the architect's Interim Certificate No 29. The amount was £188,000.
The architect had issued a non-completion certificate on December
14, 2005. The only obstacle to the employer deducting liquidated
damages was the issuing of two notices to satisfy the remaining
conditions. The first notice was the general notice that the
employer might deduct liquidated damages. This was issued on January
17, 2006, and stated that he intended to deduct liquidated damages
for the period from December 14, 2005, to the date of practical
completion.
The withholding notice relating to IC No 29 had to be issued not
later than five days before the final date for payment on January
20. The employer issued that notice on January 17. He stated that he
intended to deduct £62,000 in liquidated damages.
Having issued both the notices and removed the remaining
obstacles for deduction of liquidated damages, the employer paid
£126,000 on January 20, which was before the final date for payment.
That would have been the end of the matter, had the architect not
granted an extension of time on January 23.
The effect was to cancel the previous certificate of
noncompletion, the first condition for deduction of liquidated
damages. The employer did not reissue the two notices to satisfy the
last two conditions. He could no longer give a notice of withholding
since the cut-off date for the notice had passed.
The extension of time meant that the amount of liquidated damages
was only £12,300.
Whether the employer was entitled to deduct £62,000 of liquidated
damages became an issue because one of the grounds on which the
contractor had terminated the contract was that the employer had
failed to make payment in full.
On January 17 the three conditions for deduction from IC No 29 of
the liquidated damages of £62,000 were satisfied.
The issue was whether a valid withholding notice ceased to be
effective when a certificate of non-completion was cancelled by the
subsequent grant of extension of time.
The contractor argued that the time at which the conditions had
to be satisfied was at the final date for payment. He relied on the
decision in A Bell and Son v CBF that, if a certificate of
non-completion is superseded, then the employer's general notice
also falls.
As to the withholding notice, it was argued that it had ceased to
be effective. Liquidated damages were not due to the employer
because the certificate of non-completion on which they are based
had been cancelled. Although the withholding notice was effective
before the cancellation of the certificate of non-completion, it
ceased to be effective after.
But the Court of Appeal held that where the three conditions were
satisfied, the right to deduct the amount of liquidated damages
specified in a notice of withholding crystallised on the giving of
the notice.
The decision in A Bell and Son v CBF was
distinguished as it was decided on a different edition of the JCT.
Under the JCT 1998 Edition the employer's entitlement to deduct
liquidated damages was to be calculated by reference to the
completion date fixed at the date of the notice. The court held that
the continuing effect of the withholding notice did not depend on
the continuing existence of the certificate of non-completion.
Key points
Liquidated damages clauses avert the legal hurdles of proving
actual loss as a result of a breach of contract.
If the employer wishes to deduct liquidated damages, three
conditions must be met:
the architect must issue a non-completion certificate.
the employer must give a general notice that it might wish to
deduct liquidated damages.
the employer must issue a withholding notice against each interim
certificate for payment stating the amount of liquidated damages it
intends to deduct from the sum due.
|