Construction News Article
 
Published Date: 24/05/2007

 

Contractors in search of lost time.

 

MANY disputes in construction involve the assessment of costs, item by item. This can be difficult, since there is seldom a complete record to prove each pound claimed. 

Claims such as wasted expenditure, loss of profit and executive time - that is, time spent by senior personnel not dedicated to any specific project - are particularly difficult to assess, even without the problem of double recovery.

The recent case of Bridge Communications v Abbey Pynford illustrates how such claims will be dealt with. Bridge employed contractor Abbey Pynford to install piled foundations in an existing factory to support a 62-tonne printing press.

The floor slab should have taken 10 days but Abbey Pynford was required to undertake remedial works, which caused a month's delay. Dust generated by the remedial works had to be cleaned up and this further delayed the installation of the printing press. Abbey admitted liability, but challenged quantum. Three of the heads of claim are of particular interest.

Bridge made a claim for executive time, which was not supported by timesheets. The executive concerned had made a retrospective assessment of the time spent by looking through the various documents that recorded what happened.

Judge Ramsey followed previous court decisions in which it was held that the cost of wasted staff time was recoverable even though no loss , in the form of additional expenditure, could be shown.
The proviso was that it had to be demonstrated with sufficient certainty that the wasted time was directly attributable to Abbey Pynford's default.

Bridge had to be able to show some significant disruption to its business and that staff had been significantly diverted form their usual activities.

In this case, the evidence was that Bridge's turnover had increased from about £2 million in 2002 to an estimated £10 million in 2007. The executive whose time was at issue was the business development director, so it was accepted that his time would have been spent in selling and marketing, rather than dealing with the problems caused by Abbey Pynford.

As to the valuation, Judge Ramsey accepted the method used to assess the hours spent.

He referred to the 2001 case of Holman Group v Sherwood, where it was held that in the absence of records, evidence in the form of a reconstruction from memory was acceptable.

But Judge Ramsey observed this was an approximation of the hours spent so he applied a discount of 20 per cent to take account of any uncertainty.

For the hourly rate, the judge accepted a calculation based on the executive's annual income from the audited accounts using 2,080 hours per year. He awarded £4,800.

The claim for wasted expenditure and profit was trickier and fell into two parts.

The first part was the cost of outsourcing the printing work.

Due to the delay, Bridge had to send printing work to other firms, which of course charged for the use of their printing presses and operating personnel, together with a certain amount for consumables such as ink, power and similar items.

The costs claimed by Bridge were based on invoices.

Bridge also needed transport to deliver paper and plates and to collect printed material, and those costs were based on estimates of rates per mile.

The second part of the claim was for the wages and national insurance contributions of operatives engaged by Bridge to operate the printing press and the hire cost of the printing press during the delay.

The issue was whether Bridge could recover both parts of this claim. The general position is that it is not possible to recover both the gross return or profit expected under the contract and also the wasted expenditure. A split claim is justified only if it can be shown that there is no overlap.

The critical evidence appeared to be that if the printing press had been operational, then Bridge would have been able to perform the work that was outsourced and other work which it was unable to accept.

This was shown by the increase in turnover once the press was operational. Judge Ramsey held that Bridge was entitled to recover the loss of profit on the outsourced work and the loss of profit on the work it refused.

On the first part, the valuation of lost profit on the outsourced work was based on the additional expenditure this entailed. Bridge had already incurred the cost of the hire of the printing press and the salaries of the printers and therefore the costs of the outsourced printers were additional costs.

The judge made an adjustment of 15 per cent for consumables which Bridge would have incurred in any event, and awarded nearly £24,000.

On the second part, the judge considered that it was likely that, in the relevant period, Bridge had turned away more work than it had outsourced.

Bridge had lost profit because it had incurred the rental value of the printing press and the printers salaries without any return for the work that would have been carried out had the press been operational. This depressed Bridge s profits.

Judge Ramsey referred to the 2005 case of Carisbrooke Shipping v Bird Part, in which there had been a loss of benefit of the work of a superintendent's time when he was taken away from his usual duties.

In that case, it was decided the cost of the employee s time could be taken as an approximation for the loss of revenue.

Adopting that approach, Judge Ramsey assessed Bridge's loss of profits as equal to 50 per cent of the rental charge and printers salaries and accordingly awarded Bridge £10,881.

Finally, Judge Ramsay considered the claim for interest.

He ruled it should reflect the cost of borrowing. He referred to Tate & Lyle Distribution v GLC (1982), in which it was noted smaller firms could borrow at 3 per cent over the minimum lending rate. He decided Bridge fitted this category.

Provided it is shown that there has been some loss caused, then the court will try to value the loss. The principles are generally applicable to construction.

Key points

In Bridge Communications v Abbey Pynford the cost of wasted staff time was recoverable even though no loss , from additional expenditure, could be shown.

In the absence of a record of hours worked, evidence in the form of a reconstruction from memory is acceptable.
A split claim is justified only if it can be shown that there is no overlap between the two claims.

Claims for interest may be assessed according to the borrowing rate appropriate for the size of business.