Construction News Article
 
Published Date: 07/07/2005

 

How to engineer a settlement

 

CONVENTIONAL construction contracts provide for an Engineer or Architect (the initial capitals distinguishing their role from that of other engineers or architects working on the project) to act for the employer and to administer a contract.

An Engineer in this role has two functions. One is to act on the employer's instructions whether he agrees or not.

The other is to use his judgement on matters such as valuations, the existence of defects, entitlements and in deciding disputes referred to him.

In this second function, the Engineer is required to reach decisions fairly, holding the balance between the employer and the contractor.

When adjudication was introduced in 1998, expectations of how a dispute should be resolved changed. People became more aware of "impartiality" and "natural justice". This has led to the role of the Engineer being reconsidered. Two recent cases provide insights.

The first is the judgment of Judge Jackson in Costain v Bechtel (May 20, 2005). One issue was whether or not the project manager under a contract based on the New Engineering form of contract was required to act impartially.

Under NEC the Engineer's role is largely taken by the project manager, which in this case was a consortium ? RLE ? of which Bechtel was a member. Most of the RLE personnel working under the contract were Bechtel employees.

Bechtel argued that in NEC, the role is different to conventional construction contracts because it was more specific and contained more objective criteria.

Judge Jackson did not accept this. He said there were instances in NEC where the project manager had to exercise independent judgment to determine whether criteria were met and what precisely should be paid to the contractor.

Bechtel put forward a number of other arguments as to why the project manager was not required to act impartially, such as: that his decision is not final and that only the adjudicator has an express obligation to act impartially ? none of which convinced the judge.

He held that when the project manager under the NEC exercises his discretion in the residual areas, he was required to act impartially.

The second case is the judgment of the Court of Appeal in Amec Civil Engineering v Secretary of State for Transport decided on March 17, 2005. This case concerned the role of the Engineer under the ICE form of contract.

The Highways Agency had referred a dispute with Amec to the Engineer's consultant Pell Frischmann to be decided under Clause 66, a pre-condition to arbitration. At the same time the Highways Agency informed Pell Frischmann that it (Pell Frischmann) was responsible for defects in the works. The Highways Agency was thus in dispute with both the contractor and the Engineer.

The Engineer decided that Amec's work was defective and that it was in breach of contract.

The matter proceeded to arbitration. Amec challenged the jurisdiction of the arbitrator on several grounds, including the assertion that the Engineer's decision had been invalidated by his failure to observe a duty of fairness.

Amec alleged, for instance, that it had not been given a copy of the Highways Agency's request for a Clause 66 decision; that it was not given an opportunity to make submissions to the Engineer; that the Engineer had substantially drafted his decision before receiving the formal request for a decision under Clause 66; and that the Engineer reached a decision with undue speed.

Amec also alleged that the Highways Agency's parallel claim against the Engineer caused a conflict of interest.

Appeal Court judge Lord Justice Rix observed that if there had been no reference to arbitration and the Highways Agency had instead relied solely on the Engineer's decision as a final and binding resolution of its dispute with Amec, then the invalidity of the Engineer's decision would mean the case against Amec would collapse. But even if the Engineer's Clause 66 decision was invalid and unenforceable, that did not affect the arbitrator.

Under Clause 66, the failure of the Engineer to render a decision within three months of a reference allows either party to refer the dispute to arbitration ? so a valid decision by the Engineer is not a pre-condition of arbitration. The Court of Appeal made observations on the role of the Engineer:

Lord Justice May stated that the rules of natural justice were formalised requirements of those who acted judicially.

Compliance with them was required of judges and arbitrators and those in equivalent positions, but not of an Engineer giving a decision under Clause 66 of the ICE Conditions.

The Engineer's decision is not reached by a judicial process.

Under Clause 66 the Engineer is required to act independently and honestly. "Impartiality" does not overlay independence and honesty with a need for natural justice.

Lord Justice May recognised that circumstances could arise in which the Engineer would use his knowledge of the project, and would properly make a decision under Clause 66 on request from one or the parties without formal reference to the other.

The Engineer could give a speedy decision where the limitation period for arbitration was a problem. The Court of Appeal decided that the decision was valid. The role of the Engineer in deciding disputes is not the same as an adjudicator's and the full judicial requirement of natural justice does not apply.

Key points Under conventional contracts, the Engineer or Architect must administer the contract, using his knowledge to decided disputes between the Employer and the Contractor Under Clause 66 of the ICE Conditions, an valid decision by the Engineer is not a precondition to arbitration An Engineer or Architect must act impartially and fairly in deciding disputes. But 'natural justice' does not apply.