Delay and Disruption - The Monitor Role of the Programme

© Daniel Atkinson 2001 22 November 2001

 

Meaning of Programme
Type of Programme
Role of Programme
Obligations as to Programme
Programme as a Contract Document
SubContractors and the Main Contract Programme
Standard Forms

 

SUMMARY
There are two main roles for programmes in the management of projects, the Monitor Role and the Dynamic Role.  Five functions of programmes can be identified, three fulfilling the Monitor Role and two the Dynamic Role.  The role assigned by the contract and the particular terms will define which of the five function programmes is required.

The Monitor Role is described in this Article together with the functions of the three programmes Milestone Programme, Progress Programme and Prediction Programme. The Monitor Role of the programme allows the extent of each party's compliance with their time obligations to be assessed.

1.   The Milestone Programme is the simplest programme and allows compliance with the obligation to complete by specified dates to be ascertained at the specified time for compliance by comparing actual completion with the specified date.  The most usual type of programme is a simple schedule of dates.
2.   The Progress Programme allows the parties' planned progress to complete to be monitored.  The programme also allows the obligation to progress the work to be monitored.  The most usual type of programme is the Bar Chart.
3.  The Prediction Programme allows the likelihood of complance with the obligation to complete by a specified date to be predicted based on a comparison of progress with the planned programme using logic links.  The Linked Bar Chart is the most usual type of programme.

 

The Monitor Role of the Programme

A programme will allow the performance of time related obligations to be monitored.  The function of the programme will depend upon the terms of the contract, although frequently the parties adopt a programme for practical common sense reasons despite the absence of a contractual requirement.  The three functions of a programme used for monitoring are given below:

  1. Monitor Role
    1. Milestone Programme
    2. Progress Programme
    3. Prediction Programme

The dynamic role of the programme is described in the Article Dynamic Role and includes an additional two functions as follows:

  1. Dynamic Role
    1. Management Programme
    2. Compensation Programme

Function 1 Milestone Programme

The first function of the programme is to identify the dates when actions, information and other interfaces are required to be carried out. This may include supply of information by the Employer, the carrying out of work by the Employer or Statutory Authorities or Undertakers. The programme may also identify important milestones which are required to be achieved by the contractor to allow the Employer to carry out other parts of the project.

In order to be effective there must be contract mechanisms to revise the dates for specified risk events.  These are usually extension of time clauses.  How the compensation is determined using programmes, if this is necessary,  is examined in Function 5 - the Compensation Programme.

If this first function is the only function of the programme, then it can be fulfilled in many cases by a simple schedule.  It may be referred to as an Information Release Schedule or Interface Coordination Schedule and need only list the information or activity, the date for performance and the responsibility for performance.

Function 2 Progress Programme

The second possible function of the programme is to allow both parties to monitor the contractor's progress towards compliance with the obligation to complete the works by the specified date, or to complete sections of the work by the specified dates. To be of any value the progress must be monitored before completion occurs, which requires the progress of each of the activities to be compared to a plan. That plan is the programme of works.  The actual progress of activities can be compared with the planned progress.

There are significant limits to this method of monitoring. Some activities may take longer than planned, others less. Some risk events predicted in the model represented by the planned programme may not materialise or may not have the effect anticipated. The comparison of actual to planned progress will be a reasonable indication of progress, but only if the construction logic of the programme is actually adopted. Caution is required because a programme is only one model of how the work can be carried out. Actual progress may be different for a number of reasons, not least that risk events may or may not occur, performance may improve at a later stage in the duration of an activity or the method of working may be changed requiring greater initial preparation followed by rapid progress.

The Bar Chart is the type of programme which allows this type of monitoring.  An example is shown to the left for the "Equipment Project".

The planned programme for each activity is shown as bars with estimated durations and start and finish dates.  If the actual progress is plotted on the Bar Chart, then an indication of progress is shown.  In the example given the activity "Procure Supplier" is shown as starting late, of taking the duration planned and finishing late.  The impact of a start later than planned on other activities cannot be analysed since there are no logic links between activities.  The effect on completion also cannot be analysed logically and reliably.  Information not shown on the programme needs to be used.

It is usual when monitoring progress by this method to do so against a "TimeLine".  This is shown in the example above for the "Date 2.5".  This shows that the activity "Install Piles" started on time, but a prediction of completion based on the planned duration will be incorrect as in this example piling progressed faster than planned.  The "TimeLine" method may not therefore provide accurate predictions of future progress.

 

One solution using the Bar Chart is to use a "Rate of Progress TimeLine".  An example is shown to the left for the "Equipment Project".  In this type of monitoring the TimeLine is adjusted at each activity on the planned programme to show the percentage completion of each activity.  The Line then shows whether or not the activity is on time to the planned programme and the approximate time remaining for each activity.  The method has little analytical value for predictions of completion but is useful for identifying trends in progress if a series of TimeLines are compared.  The method has little analytical value if actual progress differs substantially from the plan.

Function 3 Prediction Programme

The third possible function of the programme is to provide a means of up-dating the prediction of future progress.  In order to fulfill this function the programme must model the time characteristics of the project.  Inevitably the programme must model the inter-relationship of activities through Logic LinksThe Linked Bar Chart is the type of programme that will fulfill this role.  An example is shown to the left for the "Equipment Project" and is described in the article Linked Bar Chart.  If the linked programme is updated to include the actual and predicted effect of events and changes in duration and logic, then modern software will allow accurate predictions of future progress.  In practice in many situations and projects, particularly repetitive trade subcontracts or in logically linear works such as tunnels or roads, the logic may be simple and will not require computer software except for presentation.

If actual progress differs from planned, then the planned programme loses its effectiveness as a means of predicting future progress. If however the programme is revised to show actual progress of activities, revised to show changes in the construction logic and the incidence of actual events, then the revised programme will provide a more accurate means of monitoring progress.  The management of information to provide accurate revisions to the programme requires considerable effort.  The information is required on an interim basis during the execution of the activity.

The personnel managing day-to-day activities may not have an overall view of the project and may not recognise or report changes in the planned rate of progress or changes in the method of working.  A systematic approach to recording and reporting is required which may involve some or all of the following:

  • Measurement of Work: - a comparison of actual to estimated measure of work may provide an indication of the rate of progress as well as identifying changes. This method of monitoring is the minimum required to accurately record progress. In some contracts the method of payment will require an estimate of percentage completion of activities or stages, or a measure of bill items.  This information can then usefully be used to measure progress.

  • Valuation of Resource Cost: - a comparison of the actual rate of expenditure of resource to the estimate may indicate that a change to the planned programme is required;

  • Productivity Measurement: - a comparison of actual productivity to estimated will identify the validity or otherwise of the assumptions made for the planned duration of activities.  This information is usually readily available to those involved on a day by day basis, but very difficult to analyse later due usually to lack of records.  A systematic approach to records such as labour allocation sheets and/or on-going histrograms is needed.  Work sampling may be sufficient in many cases, particularly when warned by those involved on a day-to-day basis.

  • Management Briefings: - Regular team briefings in which progress in terms of start and finish dates, durations, productivities, method of working and inter-relationship of activities is examined will allow a "project-wide" view to be developed.  This type of review brings together the team knowledge of recent events, increases awareness and increases the accuracy of reporting.  It is vital that the result of such analytical briefings are recorded and if necessary incorporated in revised programmes.

The initial planned programme is only one model of the way in which the works could proceed.  It is important when recording changes to recognise that the initial plan may be incorrect, either under- or over-estimating productivity or durations or the effects of risk events.  Some changes to the planned progress are therefore not the result of external factors but of the inaccuracies inherent in the planned programme.  Whenever one assumption in the planned programme is shown to be inaccurate by actual events, other similar assumptions may need to be revised.

 

PRACTICE NOTE
A distinction needs to be made between programmes required by the contract and the related obligations, and programmes required to manage the project and establish entitlement.  Frequently the two types of programme required are not the same.  In order to identify the programme and information necessary to satisfy both requirements the following steps should be taken at the commencement of the project and periodically reviewed:

   1.    Examine all the terms of the contract to establish whether a programme is required, the function of the programme and the type of programme to fulfill the function.
   2.   Examine the extension of time clauses to establish how compensation is to be assessed and the party responsible for providing evidence and the party (or A/E) responsible for assessment.  Identify the type of programme and information required.
   3.   Choose and prepare/obtain the type of programme to fulfill both functions.
   4.   Prepare pro-forma to keep records required, identify likely key evidence and the management system to integrate the evidence in progress reports.