Delay and Disruption - The Purchaser's Obligations as to Time

© Daniel Atkinson 2001 18 November 2001

 

Express Obligations
Implied Obligation Not to Hinder
Implied Obligation to Cooperate
Possession of Site
Obtaining Permits
Appointing A/E
Instructions/Supply of Info
Practice Note 1

 

SUMMARY
The Employer is required to complete his obligations specified in the contract at such times as to permit execution and completion of the Works by the Contractor at the times specified in the Contract.
Terms may be implied in the absence of express terms to the contrary which are the negative obligation not to hinder the contractor and the positive obligation to cooperate as necessary.

 

1. Express Obligations

The Employer is required to complete his obligations specified in the contract, such as supplying information, giving possession, executing any work or providing any materials, at such times as to permit execution and completion of the Works by the Contractor at the times specified in the Contract. If no such times are specified the Employer must carry out his obligations at reasonable times having regard to the date of completion of construction, the provisions of any approved programme of work and the actual progress of the Contractor.

These obligations of the Employer do not require that he should comply with the provisions of the approved programme of work, but only that he should not hinder the Contractor from carrying out his obligations to complete the works at the times specified in the Contract. It is only if no time is specified that the approved programme is relevant, and then only in establishing what are reasonable times. This therefore is not an obligation to positively co-operate with a Contractor to complete prior to the date provided for in the Contract. The situation will, however, be different if the programme is incorporated in the contract as a contract document or if the express terms of the contract state otherwise.

Terms may be implied in the absence of express terms to the contrary which are the negative obligation not to hinder the contractor and the positive obligation to cooperate as necessary.

 

2. Implied Obligation Not to Hinder

A term will usually be implied in a construction contract, in the absence of express terms to the contrary, that the Employer will not hinder or prevent a contractor from performing the contract or delay him in performing it London Borough of Merton v Stanley Hugh Leach Limited (1985) 32BLR51.

The term is implied if it is necessary for the business efficacy of the contract. Such a term may not affect certain actions by the Employer if on a proper interpretation of the contract, the Employer was entitled to take such actions. In William Cory & Son Ltd v London Corporation [1951] the contracting statutory authority was not in breach of contract in making bylaws which made more expensive the contractor’s execution of the contract. It was not intended that the statutory authority should be prevented from carrying out its public duty. If on the other hand the Employer interferes with the contractor’s method of working, in the absence of express provisions allowing him to do so, the contractor will be entitled to recover damages for breach of contract. Similar considerations apply if contractors employed by the Employer interfere with the contractor’s performance of the Contract.

 

3. Implied Obligation to Cooperate

Generally, if it is necessary for the Employer to cooperate in order for the contractor to carry out the work, then a term will be implied (in the absence of express terms) requiring that party to do all that is necessary for him to do to complete the works London Borough of Merton -v- Leach (1988) 32BLR51. Examples of such an obligation are granting possession of the site, obtaining relevant permissions, appointing the Architect/Engineer and the issue of instructions.

A. Possession of Site

(see Article on Possession and on Access)

A construction contract necessarily requires the owner to give the contractor such possession, occupation or use as is necessary to enable him to perform the contract The London Borough of Hounslow v Twickenham Gardens Development (1970) 78BLR89. In a new project a term would normally be implied into a construction contract (in the absence of an express term) that the site would be handed over within a reasonable time and, in most cases, with a sufficient uninterrupted possession to allow the contractor to carry out his obligations by the method of his choice: the Canadian case of Penvidic Contracting Co Ltd v International Nickel Co. of Canada Ltd [1975]53 DLR 748. If a contract contains an "entire agreement" clause, this will not prevent the implication of a right to possession without clear words Milburn Services Limited -v- United Trading Group (UK) Limited (1995)52ConLR130

The degree of possession or access provided by the Employer will vary with the circumstances. Generally more than the actual site on which the structure stands is required to erect the structure. The Employer is normally required to give possession of sufficient portions of the site of the work to permit compliance with the Contract: the Canadian Case of The Queen in Rights of Canada -v- Walter Cabbott Construction Ltd (1975) 21BLR26.

B. Obtaining Permits

It will depend upon the particular terms of the contract and the circumstances of the contract whether or not a term will be implied that the Employer is under an obligation to obtain building permits Ellis-Don Ltd -v- The Parking Authority of Toronto (1978) 28BLR106

C. Appointing Architect/Engineer

The Employer is under an obligation to appoint the Architect/Engineer (if expressly part of the contract machinery) to carry out the administrative functions under the contract and to appoint a replacement if the Architect/Engineer is unable to act Croudace Ltd v London Borough of Lambeth [1986] 33BLR20.

For those Architect/Engineer duties carried out on behalf of the Employer, there will be an implied warranty from the Employer that the Architect/Engineer is reasonably competent and will exercise reasonable skill, care and diligence in carrying out his duties under the contract London Borough of Merton -v- Leach (1988) 32BLR51.

Usually no term will be implied requiring the Employer to oversee or supervise the Architect/Engineer`s functions of certification and decision making under the contract. If there is an arbitration clause the parties will normally agree to the arbitrator having the power to open up, revise and review any certificates, decisions or opinions. In the absence of an arbitration agreement the parties frequently agree to the Courts having the same power. In such cases, if the contractor wishes to challenge any interim decision, he can request the appropriate adjustment in the next stage of the process or if this is refused go to arbitration or the courts to have the decision corrected. There will therefore be a formal remedy for the A/E’s failure.

If there is no power either by an arbitrator or the Courts, to open up, revise and review decisions then a contractual duty will be implied that the Employer should oversee or supervise the A/E`s functions. It is suggested however that this duty is easily discharged by the Employer.

D. Instructions and Supply of Information

If not expressly set out in the contract, it is an implied term as a matter of business efficacy that the Employer will have the details and instructions necessary for the execution of the works provided, by the Architect/Engineer or otherwise, in a reasonable time. What is a reasonable time does not depend solely on the convenience and financial interest of the contractor, but also on the Architect/Engineer, Employer and the planned order of the works and timing of requests for information Neodox Ltd v Borough of Swinton and Pendlebury [1985] 5BLR34.

The obligation to cooperate does not extend to providing information to allow the contractor to complete early Glenlion Construction Ltd v The Guiness Trust [1987] 39BLR89.

 

PRACTICE NOTE 1
Most standard forms of contract will state the obligations of the Purchaser as to time, and make clear the responsibility for obtaining permits and access etc.
The main issue in most contracts will be the timing of the issue of information by the A/E.
If the works are progressing smoothly in accordance with an agreed programme then there is little difficulty in ascertaining when information is required. It is when delays or disruption occurs that difficulties arise. In that case there may be no up to date programme. In that case dialogue is essential, but frequently does not occur.
The positive approach is to instigate meetings between the parties to discuss the requirements for information. In any event records of unfolding events will be necessary for any claims for or rebuttal of delay and disruption entitlement.