STANDARD FORMS OF CONTRACT
IChemE Forms -- Red, Green and Yellow
Lecture One: The RED BOOK
Basis of Contract and Construction
- Agreement
- Contract Documents
- The Parties
- The Project Manager
- Variations
- Extensions of Time
- Programme of Works
- Notice
- Liquidated Damages
- Certificates
- Unforeseen Conditions
Lecture Two: The RED BOOK Payment, Defects and Dispute Resolution
- Payment
- Fitness for Purpose
- Materials and Workmanship
- Remedial Works
- Exclusion Clauses
- Expert
- Arbitration
- Adjudication
Lecture Three: The GREEN BOOK
- Risk allocation
- Cooperation with Employer
- Monitoring Costs
- Quality of Work
- Time
- Liability
Lecture Four: The YELLOW BOOK
- Payment
- Time
- Quality of Work
- Disputes
|