STANDARD FORMS OF CONTRACT

NEC3 (The New Engineering Contract)

 

Lecture One:
Introduction and Comparison with other Forms of Contract

    • Background and Development of ECC
    • The Latham Report and Its Effects
    • The Construction Act 1996
    • Partnering
    • Options
    • Words/Language
    • Non-Confrontational Approach
    • Contract Formation
    • Programme
    • Remedies
    • The ECC in Practice

Lecture Two: Structure of the ECC

    • Drafting Objectives
    • Published Documents
    • Contract Documents
    • Main Options
    • Secondary Options
    • Schedule of Cost Components
    • Contract Data
    • The Parties
    • The Project Manager
    • Designers
    • The Supervisor
    • The Adjudicator
    • The ECC Sub-Contract
    • Professional Services Contract
    • The Adjudicators Contract

Lecture Three: Main Options and Secondary Options

    • Contract Strategy
    • The Six Main Options
    • Option A - Priced with Activity Schedule
    • Option B - Priced with BQ
    • Option C - Target with Activity Schedule
    • Option D - Target with BQ
    • Option E - Cost Reimbursement
    • Option F - Management Contract
    • Bonds and Guarantees - Options G,H and J
    • Payment Provisions - Options J, K, N, P and Q
    • Sectional Completion and Damages - Options L, R and S
    • Law - Options T, U and V
    • Design Liability - Option M

Lecture Four: Contract Creation, Obligations, Programmes and L.D's

    • Tender Documents
    • Form of Tender
    • Contract Data
    • Works Information
    • Site Information
    • Co operation and Good Faith
    • Communications
    • Early Warning
    • Providing the Works
    • Contractor's Design
    • Assignment
    • Sub Contracting
    • Contract
    • Contract Date
    • Starting Date
    • Access/Possession/Completion
    • The Accepted Programme
    • Acceleration

Lecture Five:
Testing, Defects, Payments and Compensation Events, Disputes Resolution and Termination

    • Liability for Defects
    • Remedying Defects
    • Construction Period
    • Defects Certificates
    • Post Correction Period
    • Prices
    • PWDD
    • Actual Cost
    • Compensation Events
    • Quotations
    • Notices
    • The Adjudicator
    • The Tribunal
    • Termination